docs(records): row 25 approver fix, second Discord restart, SetSpark approver and docker network gaps
Co-Authored-By: Claude Opus 5.5 <[email protected]>
This commit is contained in:
@@ -114,6 +114,20 @@ at every gate. Started 2026-09-12 during the control board MVP.
|
||||
of the runtime files. Until then the rule is that unreviewed Discord source
|
||||
stays uncommitted in the tree only as long as a review needs it.
|
||||
(2026-09-26, #1509)
|
||||
- **SetSpark service accepts any string as a decision approver.** Create
|
||||
checks only that `required_approvers` are distinct non-empty strings, and
|
||||
approval checks `discord:<author id>` against them. So a decision stored
|
||||
with names (DEC-009) can never be approved, and nothing says so until
|
||||
an approval is tried. Mosaic's connector now writes only `discord:<id>`
|
||||
(20ea5a0b), but the service should refuse other shapes. This belongs to
|
||||
shared-signals, not Mosaic. Reported to Jason. (2026-09-26, #1509)
|
||||
- **Index-export suite runs leave Docker networks behind.** Each export
|
||||
directory becomes a compose project, and its `<dir>_default` network
|
||||
stays after the run. On 2026-09-26 the host ran out of address pools. The
|
||||
task and release suites then failed 31 and 3 tests with "all predefined
|
||||
address pools have been fully subnetted". Sage removed its own five stale
|
||||
networks. The dw-* ones are still there. Fix: the export recipe, or the
|
||||
suites, removes the project network on exit. (2026-09-26)
|
||||
|
||||
## Queue
|
||||
|
||||
|
||||