jason.woltjeandClaude Opus 5.5 fd72d26899 feat(ledger): Piece E, queue section in the weekly ledger (row 13, #1508)
The ledger prints a queue section above the weekly table. It checks four
things:
- open issues named by done rows;
- owner registrations for active rows;
- closed issues for done rows;
- the age of required rows.
The result is fail, incomplete or reduced pass. It uses its own Gitea
budget of the open list plus at most 10 lookups. A full open page counts
only while an issue in some row's closes has no known state (lead
decision 40). T3 seats are exempt per run with --unsupported-runtime.
The weekly routine is in packages/ledger/README.md.

Built by Darkwing (build.patch ab1f12ca, manifest 0b20bbca). Filbert
reviewed it: round 1 81f26f2e asked for changes (C1, ISO requiredSince
never aged); round 2 ce8ce150 approved. Also carries Filbert's plan
amendment for decision 40 (68a25ffe).

Co-Authored-By: Claude Opus 5.5 <[email protected]>
2026-09-27 11:33:44 -05:00
jason.woltjeandClaude Opus 5.5 f539466fcb feat(queue): Piece D, reviews as issue comments, raw per-seat token helper (row 12, #1508)
queue move ID in-review posts the review request as a Gitea comment and
review record reads verdicts back, so reviews stop being files in
docs/plans/reviews/. On a comment round, in-review to waiting-on-jason
now needs every listed reviewer's approval for the current round, the
same as in-review to done (Filbert r1 C1). scripts/gitea-api.sh reads
the raw per-seat token files (lead decisions 37 to 39): config built and
checked before curl starts, export attribute cleared, fixed base URL.
test-queue.sh skips its live checks outside the canonical root.

Darkwing authored. Filbert approved D r2 (cf1d3fd0) after r1 (a2dc2302)
and corrected the plan (293747cd). Rocko reviewed the helper (e896192f,
2096b0a3), and Sage's lead check passed under decision 38. Manifest
b402fb38, 19 files.

Co-Authored-By: Claude Opus 5.5 <[email protected]>
2026-09-27 10:07:29 -05:00
jason.woltjeandClaude Opus 5.5 1c5f6bc3a0 docs(queue): queue-as-data plan round 6, Rocko approved (#1508)
Plan 282fabbb (Filbert) and the six adversarial rounds (Rocko, r6 80cde839).
Lead item 15: Gate F first, then A1 and A2 as separate reviewed commits.

Co-Authored-By: Claude Opus 5.5 <[email protected]>