Brief for one queue row. Written by Sage on 2026-10-04 after Jason's ruling on row 7 (lead decision 42, item 7): "We are chasing a metric that may be useless. A good starting point perhaps, but we will need to augment the guideposts over time." It's also the second brief toward row 11's gate.
Ledger: Jason's overhead per finished piece, unattended pieces, rework and wait time
Problem
The ledger's one success number is human messages per closed issue
(packages/ledger/src/ledger.mjs, humanMessagesPerClosedIssue). The
2026-09-28 run gave 33.0 against row 7's gate of under 10. The number
counts every message Jason sends to a mosaic-stack T3 thread the same way.
A ruling he alone can make ("1. pass" on Gate G) counts the same as a
message he shouldn't have had to send: launching a seat, relaying between
seats, finding a credential, correcting an agent, or asking "Did you
actually start?" after Sage said it had. The goal is for Jason's time to go
to decisions, not admin, and the current number can't tell the two apart.
It also divides by Gitea issues, while work is done and accepted per queue
row.
Owner and reviewer
- Owner: darkwing, who built the ledger's queue section (Piece E).
- Reviewer: filbert.
Files owned
packages/ledger/src/ledger.mjs,packages/ledger/src/cli.mjs,packages/ledger/src/t3.mjs,packages/ledger/src/queue-checks.mjs- a new
packages/ledger/src/guideposts.mjsif the owner prefers to keep this apart packages/ledger/tests/(new or changed test files and fixtures)packages/ledger/README.md(the guideposts section and the weekly routine)
What ships
All four measures cover the run's date range. Each prints next to the current totals line, which stays unchanged.
- Overhead per finished piece (the headline). A tag file named with
--tags FILElists Jason's in-range mosaic-stack messages by T3 message id.- Each entry is
{ "id": "<message_id>", "kind": "decision" | "overhead", "row": <id or null> }. An overhead entry also has"why": "launch" | "relay" | "credential" | "correction" | "status" | "other". - The file holds ids and tags only, never message text. The ledger prints no transcript, and the tag file doesn't either.
- Overhead per finished piece is overhead messages divided by rows that
moved to
donein range, read from the queue log. - Every in-range human message id the ledger counts must be tagged. An
untagged id, a duplicate, an unknown id or an unknown kind makes the
measure
incompleteand names the ids. It never guesses. - Without
--tags, the measure printsnot tagged.
- Each entry is
- Unattended pieces. Of the rows done in range, the share with no
overhead message tagged to them. Overhead tagged
row: nullcounts in measure 1 but not here, and the output prints that count. - Rework. For rows done in range, the review rounds and the
changesverdicts in the queue log, per row and as a total. - Waiting on Jason. For each row that sat in
waiting-on-jasonduring the range, the hours it spent there, from the queue log's moves. This one is reported, not scored. It shows where the queue stalls, not a mark against Jason.
The --json output carries the same fields. Tests use fixture queue logs,
fixture T3 databases and fixture tag files covering:
- every refusal above;
- a row closed and reopened in range;
- a range with no done rows, where the per-piece measures print
nonerather than dividing by zero.
node --test packages/ledger/tests/ and bash scripts/test-queue.sh pass.
The README's weekly routine gains one step. Sage writes the week's tag
file at agents/sage/work/ledger/<date>_tags.json, commits it with the
run, and Jason corrects any tag by saying so. Sage commits the correction
as a new file, never by editing the old one.
Out of scope
- Row 7's gate and whether these measures replace the current number. That stays Jason's decision once a few weeks of runs exist.
- Automatic tagging by a model. Sage tags by hand at first, and the ledger only checks the file.
- Corrections recorded in BUILD-LOG and fixes after a commit. Neither has a machine-readable form yet, so they wait on that.
- Messages in other T3 projects. The ledger already scopes T3 to the mosaic-stack project.
Gate
Filbert approves through the queue (queue review record). Then Sage
commits the candidate, and the suites above must pass on it. Before
closing, Sage runs the ledger with --tags on the 2026-09-27 to
2026-10-03 week and posts that run on #1514 next to the plain run.