QUEUE — the one task list

Read this first. One row per piece. Nobody needs to read the prose plans to know what is next; the Brief column says which section to open only when you are the owner of that row.

How to find your next thing:

  • Jason: the first row whose State starts with Jason:.
  • A seat: the first row where Owner is you and State is in progress, in review or briefed. If there is none, you have nothing; say so on the board and stop.
  • Coordinator (Claude session): update this table at every gate, before anything else is written. CURRENT.md is the narrative log; this table wins if they disagree.

States: queued (no brief yet) → briefed (brief written, not started) → in progressin reviewJason: <what he must do>done. parked means not before the rows above it and not without Jason's say. required means it cannot be parked or reordered below queued rows; only Jason moves it.

Brief locations: "plan page" is docs/plans/2026-09-12_control-board-mvp.md. Gaps found while working go to docs/plans/DEFERRED.md, not here.

Pieces (in order)

# Piece Owner Issue State Gate Brief
1 Control board MVP (scanner + page) darkwing #1503 Jason: rule whether the page answers "who is waiting on me" without a terminal; then close #1503 and mark MOSAIC-STACK-D-001 completed A passed 2026-09-12 plan page, top
2 Seat registration and mosaic seat task darkwing #1504 done 2026-09-13 B passed 2026-09-12 plan page, Step 3
3 Reply-from-board (piece 2 on the plan page) darkwing #1505 done 2026-09-12 C passed 2026-09-12 plan page, "Piece 2: reply-from-board"
4 Ledger (piece 3 on the plan page) darkwing #1506 done 2026-09-13 D: 18.9 human messages per closed issue, week of 2026-09-06 plan page, "Piece 3: ledger"
5 WebUI first screen on the Console design (piece 4 on the plan page) dewey; filbert reviews #1507 Jason: use WebUI Monday and give Gate E ruling; ea00ec66 published, Filbert approved, committed-tree 208/208 E: Jason works Monday 2026-09-14 from the WebUI without the terminal plan page, "Piece 4: WebUI first screen (Console)"
6 Darkwing on point: darkwing assigns and gates filbert's work (piece 5 on the plan page) darkwing none yet briefed; Jason: send the start message from the board on Sunday 2026-09-13 F: filbert's item closes with zero human messages from Jason plan page, "Piece 5: darkwing on point"
7 Weekly ledger run and rails number Jason recurring, end of Monday 2026-09-14 under 10 human messages per closed issue for the week of 2026-09-13 packages/ledger/README.md
8 Fleet seats (~/.mosaic) onto mosaic launch unassigned queued; not before row 6 is done Jason's call none yet
9 Queue as data: docs/plans/queue.json, mosaic queue is the only writer darkwing; filbert reviews #1508 required; starts when row 6 is done, before row 8 G: a fresh seat told only "run mosaic queue next and do it" starts its piece with zero human messages 2026-09-13_queue-as-data.md, Piece A
10 Seats read the queue, not CURRENT.md (AGENTS.md cadence, seat context files) coordinator #1508 required; AGENTS.md lines done 2026-09-13, rest after row 9 verified by Gate G 2026-09-13_queue-as-data.md, Piece B
11 Brief template docs/plans/BRIEF-TEMPLATE.md; queue add refuses a missing brief darkwing #1508 required; with row 9 two briefs accepted by Jason with no scope question 2026-09-13_queue-as-data.md, Piece C
12 Reviews as issue comments posted by queue move ID in-review, not files in docs/plans/reviews/ darkwing #1508 required; after row 9 one review round with no new file under reviews/ 2026-09-13_queue-as-data.md, Piece D
13 Ledger "queue" section: issue/row/seat drift printed with the weekly number darkwing; filbert reviews #1508 required; after row 9 first run Monday 2026-09-21, zero violations or every one moved same day 2026-09-13_queue-as-data.md, Piece E

Start message for row 6, sent from the board to darkwing: "Read docs/plans/QUEUE.md, then the plan page section "Piece 5: darkwing on point", and execute it. Start with the first assignment for filbert. Report at Gate F or when blocked."

Parked (not in order, needs Jason to reopen)

Item Why parked Where
Registry increment 3 (headless identity-env leak) #1500 closed on increment 2; Jason has not asked for 3 CURRENT.md, "#1500 increment 2 (historical)"
Auth/provider/harness registry review Paused for owner alignment docs/plans/2026-09-03_auth-provider-harness-registry.md
CI runners, second real adapter, push automation Deferred by owner 2026-09-03 docs/plans/ROADMAP.md, "Explicitly deferred"
Console screens beyond the first (launch, observe, stop, transcript, palette) Needs a new brief after Gate E DEFERRED.md
Open gaps from the MVP work Fixed only when a gate needs them DEFERRED.md, "Open"

Log of table changes

  • 2026-09-13 — created; rows 1 to 8 taken from CURRENT.md, DEFERRED.md and the plan page.

  • 2026-09-13 — rows 9 to 13 added (#1508): the process itself becomes data with one writer and ledger checks. Jason: "I want this iron-clad." Required, not parked; rule: these rows cannot be moved to parked, only to done.

  • 2026-09-13 — dewey: WebUI row advanced to Jason-owned Gate E after Filbert approval, exact committed-tree 208/208 and remote-verified ea00ec66 publication. No other row changed.

  • 2026-09-13 — rows 9 to 13 now point at the plan page 2026-09-13_queue-as-data.md (pieces A to E, Gate G).