D-1 RULED — corrected wire-in target is a new production Node TaskExecutor on the
LIVE dispatch path (packages/mosaic launch + packages/coord) that Coord/Forge/live
dispatch submit through. The Python rail is deleted, not ported. RM-21/26/27/52 updated.
D-2 — Jason-pending and explicitly NON-blocking. Binding meanwhile: the DB spine must
not be a single-point hard-stop; degraded mode + rollback artifact become design
requirements on RM-12/13/23/36/53. This reverses the earlier recommendation to
pre-commit 'no DB means the fleet stops'.
D-3 — RM-03 HOLD; PR #1023 marked SUPERSEDED-PENDING-JASON; RM-02/RM-55 proceed
independently since conformance assertion is not the gate-6 fix itself.
RM-03 now carries BOTH queue-guard defects: wrong exit on unknown, and evaluating
branch=main rather than the branch being pushed.
D-7 — shared 30G /tmp hit 100% ENOSPC, degrading two seats. ~5.2G of it is session
scratch dead for 8-9 days; this session's own footprint is 88K. Same missing
capability as P-FLEET-001 stale-session GC, applied to disk. Folded into RM-50, and
RM-01 gains artifacts-off-shared-tmp acceptance criteria.
Co-Authored-By: Claude Opus 5 (1M context) <[email protected]>
Third independent live instance of the inert-gate class this session: the mandated
ci-queue-wait.sh returned exit 0 on state=unknown while guarding a push.
Co-Authored-By: Claude Opus 5 (1M context) <[email protected]>
TASK-1 complete. planner-opus (robustness, 38 tasks/8 dissents) and planner-sol
(pragmatic, 25 tasks/10 defers/7 dissents) each decomposed the 4-build plan without
seeing the other's work. Both decomps are committed alongside the reconciliation so
the disagreements stay auditable rather than being flattened into a consensus.
Reconciled into 58 tasks across P0-P5 (docs/remediation/TASKS.md):
- 7 independent convergences, treated as settled because neither planner could see
the other. The headline: BOTH reject the charter's wire-in point
(mosaic_orchestrator.py::run_single_task) because that controller is disabled and
references a dispatcher absent from this checkout — wiring it would produce a
stranded executor, the same built-but-unwired disease one layer up.
- 7 genuine disagreements ADJUDICATED, not averaged. The cost estimates are ~18x
apart; rather than split the difference, the plan adopts sol's scope with opus's
rigor and treats the first-dogfood gate as a hard budget checkpoint.
- 3 decisions escalated (wire-in point, rollback artifact + availability trade,
queue-guard ownership vs parked PR #1023). No task blocked on them is dispatched.
Keystone dogfood case recorded (TASKS.md 1a): merged PR #868 shipped a file failing
pnpm format:check, then an unrelated PR reformatted it as a side effect, so main went
green and the gate's failure to fire left no trace. Detection must therefore be
per-merge-commit against that commit's own tree.
Co-Authored-By: Claude Opus 5 (1M context) <[email protected]>
Corrects the premature "DISPATCHED" planner line (per Mos): both planners are now
dispatched for real on GUARANTEED-clean context, not requested-clean.
Records Mos rulings: mission.json is retired-rail residue (do not invest); gate-16
holds on interim mos-dt-0 since rev-974 reviews; remote-control path is Mos-relay.
Captures 4 live failure classes observed while standing this seat up (D-1..D-4),
including an agent that silently ignored an in-message context reset — direct
evidence for the postmortem thesis that instructions are not enforcement.
Co-Authored-By: Claude Opus 5 (1M context) <[email protected]>
15/15 proposals decided (13 accept, 2 modify). Collapses to 4 builds + hygiene on one
PG spine + choke-point service. Durable mission record for the mos-remediation project
orchestrator; compaction-survival resume in KICKSTART.md.
Co-Authored-By: Claude Opus 4.8 <[email protected]>
Claude-Session: https://claude.ai/code/session_018XCrpMFmCAXbtSQtQAhDth